Kabul city newspaper The first part of the construction of the first part of the Bagramyoleteh road in the 22nd district of Kabul-Jalalabad road, worth 340 million afghanis, has been started.
The road is 3,300 meters long and 60 meters wide.
In the report, it is stated: Director of Kabul Municipality’s programs and projects, engineer Mirul Rahman Naseri said; This road in the eastern zone of the economic corridor is an important road, and the works should be completed within the next 18 months.
He added that currently, cleaning operations are underway in Kindno Road, Liqdulu Road, Lashtiyo Johrulu Road and 15 property acquisitions.
It is said that the construction of a bridge along the road, several culverts, flowerbeds and other places, the installation of lighting, the construction of retaining walls along the road, and the construction of curbs on the road are also fundamental parts of this project. .

Share.